June 2025 Quarterly Activities Report

28/07/2025

Liontown delivers strong first year finish with positive operating cash flows for the Quarter and underground ramp up on schedule.

We have produced over 300,000 wet metric tonnes of spodumene concentrate in its first 11 months of operation, demonstrating the successful design and ramp up of the Kathleen Valley process plant, laying a strong foundation for future growth.

The June Quarter results highlight the Company’s resilience, responsiveness to rapid market changes, capital management and continued progress against key milestones, including:

Liontown enters FY26 focused on transitioning to Australia’s first fully underground lithium operation, and unlocking long-term value through continued cost and capital optimisation while maintaining expansion optionality should the market conditions improve.